Frank Street, Peterborough — closed in, with siding going on, September 2026.
The four townhomes from above, September 2026.
Windows in and the building wrapped, ready for siding, September 2026.
Siding complete on the end unit, September 2026.
The townhomes within the neighbourhood, September 2026.
Inside one of the townhomes, with drywall in, September 2026.
A bedroom with its windows in, September 2026.
Looking through the main floor of a townhome, September 2026.
Product
Four townhomes, 4 rental homes
Status
Under construction
Metrosuite's role
Builder and construction manager
Ownership
Third-party ownership entity, affiliated with Metrosuite
Delivery method
Site-built (wood frame)
Years
2026
Four family-sized rental townhomes in Peterborough. Framing and roofing were completed in August 2026 and the mechanical and electrical rough-ins in early September; drywall and interior finishing are under way.
Frank Street is a deliberate exception to the modular default. The site, the unit type and the local trade base favoured a conventional build, and the choice was made at feasibility. Modular is how Metrosuite delivers most of its housing; housing is the point, and the method follows the site.
Milestones
Structural framing complete
August 2026
Roof complete
August 2026
Rough-ins and inspections complete
September 2026
Interior finishing
In progress
Completion
Late 2026, planned
As of September 2026. Planned dates depend on manufacturer and municipal schedules and are updated as they change.